+ 1. The following project is defined as follows: Use PERT/CPM to answer the following questions....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
+ 1. The following project is defined as follows: Use PERT/CPM to answer the following questions. You need to work this out manually without any software using AOA or AON network method. Activity ABCDEFGHLIEL J ACTIVITY AB AC AD BC Duration (weeks) Immediate Predecessors 10 BE CF DF 7 4 20 7 10 7 3882 15 11 EF FG 7 2 a. Construct the network for this problem b. Determine the early start, late start, early finish, late finish for each activity c. Determine the estimated project completion time and critical path d. Determine the slack for each activity e. What is the effect to the overall project if activity C takes 21 weeks and activity E takes 10 weeks to complete 2. On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, the remaining $17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as defined by the project manager and approved by the customer is the following: NETWORK LOGIC/ TIME (Weeks) 7 10 AURRE 8 4 А 2 3 с 2 1 B.D.E. B.DE F F G.H LI G.H On August 27, 2013, the executive steering committee received the following report indicating the status of the project as of this time (end of week 8) ACTIVITY % COMPLETE ACTUAL COST TIME REMAINING (Weeks) AB AC AD BC BE a. What is the expected completion time of this project? b. What is the critical path? START ACTIVITY c. Use Earned Value to determine the status of the project as of August 27th, by determining Cost Variance, Schedule Variance, CPI, SPI and Critical Ratio ABCDE 100 60 d. Is the project ahead of schedule or behind schedule and over budget or under budget? e. What recommendations would you make for this project? 87.5 50 50 3. Given the following PERT network for modeling a new home construction by the Bonanza Development companx (activity times are given in weeks): 133 st 3 B 3 E $23,500 $19,200 DURATION ACTIVITY DURATION 6 8 CHLIEL $37,500 $8,000 $5,500 G Н F K H 10 5 0 4 1 2 1 3 1 5 3 K FINISH a) What is the critical path and expected project completion time? b) Activity J is being performed by a subcontractor, Reliable Plumbers, who is going to be 5 weeks delayed. It will cost Bonanza $2000 per week if the project is not completed on time (within the critical path length). Reliable is charging $3000 for the plumbing activity. Bonanza has three options: > Keep Reliable Plumbers 4. Consider the following project (times are in weeks): A ACTIVITY Cancel the contract with Reliable Plumbers and hire another contractor, Local Plumbers Inc. Local Plumbers will take two weeks to complete activity J and will charge $7000. Bonanza can train its own employees who are currently performing activity E to do the work. This involves a two week training period as soon as activity E is done. It is expected it will take them three weeks to perform activity J. The cost of the training is $800 per week and the cost of them doing activity J is $1000 per week. Which alternative do you recommend? Explain? ABCDEFG NORMAL CRASH TIME TIME 12 7 844244 B 12 53193 E NORMAL COST $3,000 $2,000 $4,000 $500 $5,000 $500 $5,000 F CRASH COST $5,000 $3,500 $7,000 $1,100 $8,000 $1,100 $8,000 G & What is the critical path & project completion time? b. What is the minimal cost to crash the project to 24 weeks? c. What is the minimal time and cost that the project can be crashed? 5. Refer to the earned value chart below for a specific project and answer the following questions: DOLLARS $35,000 $30,000 $25,000 $20,000 $15,000 $10,000 $5,000 $0. EARNED VALUE 6 7 TIME LINE (weeks) 8 10 12 a. Describe what occurred with schedule and cost in weeks 1 through 5 b. Between weeks 5 and 6, was the project on schedule and within cost? Explain? c. Explain what occurred between weeks 6 through 8 with regards to schedule and costs d. Describe the current status of the project (week 10) with regards to cost and schedule -BCWS BCWP ACWP a. The probability of completing the project within 20 days b. The probability of completing the project between 17 and 21 days c. The probability of completing the project within 16 days d. The number of days to complete the project within a probability of 95% Activity A M B A B с D Activity А ABCDEFGH-KLE E F G J M a. Average time and standard deviation to complete the project b. The probability that each activity is on the critical path c. The probability of completing the project within 50 weeks 1 2 4 ABBD00 8 2 4 1 7. Consider the following project below. Assume that each time has a triangular distribution with the minimum, most likely and maximum values indicated. Use simulation to determine: А Immediate Minimum Predecessor Value 2 C,E,F,G H H I J K,L Time Estimates (weeks) Most Likely Value W74A W ON W 3 8 6 3 3 3 1 3 3 10 8 6 2 43200420 00 00 61415 8 3 5 9 5 5 2 5 5 4 2 4 Maximum Value 5 7 10 8 10 7 9 3 4 6 64 10 8 6 3 6 Immediate Predecessors A B C.D B E + 1. The following project is defined as follows: Use PERT/CPM to answer the following questions. You need to work this out manually without any software using AOA or AON network method. Activity ABCDEFGHLIEL J ACTIVITY AB AC AD BC Duration (weeks) Immediate Predecessors 10 BE CF DF 7 4 20 7 10 7 3882 15 11 EF FG 7 2 a. Construct the network for this problem b. Determine the early start, late start, early finish, late finish for each activity c. Determine the estimated project completion time and critical path d. Determine the slack for each activity e. What is the effect to the overall project if activity C takes 21 weeks and activity E takes 10 weeks to complete 2. On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, the remaining $17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as defined by the project manager and approved by the customer is the following: NETWORK LOGIC/ TIME (Weeks) 7 10 AURRE 8 4 А 2 3 с 2 1 B.D.E. B.DE F F G.H LI G.H On August 27, 2013, the executive steering committee received the following report indicating the status of the project as of this time (end of week 8) ACTIVITY % COMPLETE ACTUAL COST TIME REMAINING (Weeks) AB AC AD BC BE a. What is the expected completion time of this project? b. What is the critical path? START ACTIVITY c. Use Earned Value to determine the status of the project as of August 27th, by determining Cost Variance, Schedule Variance, CPI, SPI and Critical Ratio ABCDE 100 60 d. Is the project ahead of schedule or behind schedule and over budget or under budget? e. What recommendations would you make for this project? 87.5 50 50 3. Given the following PERT network for modeling a new home construction by the Bonanza Development companx (activity times are given in weeks): 133 st 3 B 3 E $23,500 $19,200 DURATION ACTIVITY DURATION 6 8 CHLIEL $37,500 $8,000 $5,500 G Н F K H 10 5 0 4 1 2 1 3 1 5 3 K FINISH a) What is the critical path and expected project completion time? b) Activity J is being performed by a subcontractor, Reliable Plumbers, who is going to be 5 weeks delayed. It will cost Bonanza $2000 per week if the project is not completed on time (within the critical path length). Reliable is charging $3000 for the plumbing activity. Bonanza has three options: > Keep Reliable Plumbers 4. Consider the following project (times are in weeks): A ACTIVITY Cancel the contract with Reliable Plumbers and hire another contractor, Local Plumbers Inc. Local Plumbers will take two weeks to complete activity J and will charge $7000. Bonanza can train its own employees who are currently performing activity E to do the work. This involves a two week training period as soon as activity E is done. It is expected it will take them three weeks to perform activity J. The cost of the training is $800 per week and the cost of them doing activity J is $1000 per week. Which alternative do you recommend? Explain? ABCDEFG NORMAL CRASH TIME TIME 12 7 844244 B 12 53193 E NORMAL COST $3,000 $2,000 $4,000 $500 $5,000 $500 $5,000 F CRASH COST $5,000 $3,500 $7,000 $1,100 $8,000 $1,100 $8,000 G & What is the critical path & project completion time? b. What is the minimal cost to crash the project to 24 weeks? c. What is the minimal time and cost that the project can be crashed? 5. Refer to the earned value chart below for a specific project and answer the following questions: DOLLARS $35,000 $30,000 $25,000 $20,000 $15,000 $10,000 $5,000 $0. EARNED VALUE 6 7 TIME LINE (weeks) 8 10 12 a. Describe what occurred with schedule and cost in weeks 1 through 5 b. Between weeks 5 and 6, was the project on schedule and within cost? Explain? c. Explain what occurred between weeks 6 through 8 with regards to schedule and costs d. Describe the current status of the project (week 10) with regards to cost and schedule -BCWS BCWP ACWP a. The probability of completing the project within 20 days b. The probability of completing the project between 17 and 21 days c. The probability of completing the project within 16 days d. The number of days to complete the project within a probability of 95% Activity A M B A B с D Activity А ABCDEFGH-KLE E F G J M a. Average time and standard deviation to complete the project b. The probability that each activity is on the critical path c. The probability of completing the project within 50 weeks 1 2 4 ABBD00 8 2 4 1 7. Consider the following project below. Assume that each time has a triangular distribution with the minimum, most likely and maximum values indicated. Use simulation to determine: А Immediate Minimum Predecessor Value 2 C,E,F,G H H I J K,L Time Estimates (weeks) Most Likely Value W74A W ON W 3 8 6 3 3 3 1 3 3 10 8 6 2 43200420 00 00 61415 8 3 5 9 5 5 2 5 5 4 2 4 Maximum Value 5 7 10 8 10 7 9 3 4 6 64 10 8 6 3 6 Immediate Predecessors A B C.D B E
Expert Answer:
Answer rating: 100% (QA)
Here are the stepbystep workings for the questions 1 Project network and PERT calculations a The network for the given activities is A F G H B F C E D ... View the full answer
Related Book For
Posted Date:
Students also viewed these accounting questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
The project described in the following table is scheduled to be completed in 11 weeks. Construct a network diagram using AOA or AON (see Example 5 for either type). Then answer the following...
-
Examine the difficulty of adding a proposed lwi.drd, rsl, rs2 (Load With Increment) instruction to MIPS. Interpretation: Reg[rd] = Mem[Reg[rs1] + Reg[rs2]] 1. Which new functional blocks (if any) do...
-
What is the role of a CRM system? What sort of benefits can such a system produce for a business?
-
Find an equation in rectangular coordinates for the surface represented by the spherical equation, and sketch its graph. = /4
-
A gray gas with an absorption coefficient of \(\kappa\) is contained between two plates separated by a distance \(L\). Using the diffusion approximation for radiation, derive the relation...
-
Policy Pollsters is a market research firm specializing in political polls. Records indicate in past elections, when a candidate was elected, Policy Pollsters had accurately predicted this 80 percent...
-
Let f(x)=x for rational x and f(x) = 0 for irrational x. (a) Calculate the upper and lower Darboux integrals for f on the interval [0, b]. (b) Is f integrable on [0,b]?
-
Jamie Lee and Ross, now 57 and still very active, have plenty of time on their hands now that the triplets are away at college. They both realized that time has just flown by; over twenty-four years...
-
How much to save for retirement today? How much to save for retirement every year Retirement needs at the age below: current age 45 Retirement age 67 Life expectancy 95 The current income level is...
-
Barbara Worrell and Rita Young are neighbors in Denver. Barbara works as a software engineer for Creative Games Corporation, a computer game company, while Rita works as an executive for United...
-
How should an operational manager be involved in the business-as-usual activities of managing business processes?
-
What are the components of business capability?
-
What are the four aspects of the BPM success stool?
-
Why does a one approach fits all approach not work?
-
What is the Operating Profit Margin calculation for the year 2021/2022 base on the company statement. Just use base on the company statement for the both year 2021/2022. no need to take the group...
-
Write a paper about the Working relationship in the organization- collaboration within and outside the organization
-
What are some of the trade-offs that might be factors in designing a supply chain?
-
a. Given the following forecast and steady regular output of 550 every month, what total cost would result if overtime is limited to a maximum of 40 units a month, and subcontracting is limited to a...
-
An analyst made the following observations about whether customer service representatives were busy (B) or idle (I): a. What is the percentage of idle time? b. Given these results, how many...
-
The simplified financial statements of two companies, P and Q, are shown in Figure 7.8. Assuming that interest is charged on the long-term loan at 10 per cent per annum, calculate the following...
-
For which sort of business might the ratio of receivables to sales be the lowest (and therefore the debtors collection period the shortest)? A. A market stall selling vegetables. B. An audit firm. C....
-
What is the return on capital employed? A. 39.0% B. 44.9% C. 48.0% D. 17.8% E. 34.0% Using the following balance sheet and income statement Balance sheet m Property 200 Trade payables Plant and...
Study smarter with the SolutionInn App