1 What is risk? 8 A construction project requires five major pieces of work to be...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
1 What is risk? 8 A construction project requires five major pieces of work to be completed which are independent. These five paths have variances as given in Table 10.10. Determine the probability that the project will be completed within: (a) 18 weeks. (b) 16 weeks. (c) 13 weeks. 2 Why should risk be a fundamental part of the consideration of a project manager? 3 Which other stakeholders would have an interest in the level of risk that a project presents? 4 When would a quantitative approach be appropriate and when would you use a qualitative approach to risk assessment? Table 10.10 5 What are the benefits and limitations of the quantitative and qualitative approaches to risk Expected duration (weeks) Path Variance assessment? A 10 1.21 6 Is risk assessment the same as risk management? 8 2.00 12 1.00 7 Considering the critical path alone for the project in Table 10.9, calculate the activity variances and the total variance of the critical path. From this, calculate the standard deviation. Determine the probability of the project being completed within the following D 15 2.89 E 14 1.44 9 You are in charge of a new product launch. This will be a formal press launch, where the product is introduced by your managing director and the press and major customers have the opportunity to see the product for the first time. The formalities are to be preceded by a buffet. Before hiring the catering service it is necessary to identify the guest list and invite them to determine numbers. Because of tied arrangements between certain venues and the caterers, you will have to times: (a) 30 days. (b) 40 days. (c) 42 days. Table 10.9 Activity Optimistic time Most likely Pessimistic time time 3 4 11 select the venue, then select the caterers. The launch 1 publicity materials will need to be designed, and artwork carried out before brochures can be printed. These must be available on the day. The promotional boards to be placed around the launch room should C 10 11 8 10 18 E 1 3 F 1 3 3 4 be constructed once the publicity materials have been designed. No artwork is required for these. A sound system is required and must be hired 2 2 10 J 16 20 30 K 1 1 once the venue has been identified. Table 10.11 Activity Description Optimistic time Most likely Pessimistic time Select launch venue 1 3 Design launch publicity Have artwork prepared 2 3 4 3 D Print brochures 1 4 Construct promotion stand Order sound system E 1 2 0.5 1.5 Select caterers 1 3 Develop invite list Invite and get replies H 1 1 1 J 2 3 The activities are included in Table 10.11, together 10 Choose a project with which you are familiar. For that project, identify the opportunities that such a project presents for performance or outcome over and above what has been expected or with the best estimates for optimistic, pessimistic and most likely times. The MD has asked you to set the launch date (all times are in weeks). Show the criteria that you have used, and include the network diagram. required. 1 What is risk? 8 A construction project requires five major pieces of work to be completed which are independent. These five paths have variances as given in Table 10.10. Determine the probability that the project will be completed within: (a) 18 weeks. (b) 16 weeks. (c) 13 weeks. 2 Why should risk be a fundamental part of the consideration of a project manager? 3 Which other stakeholders would have an interest in the level of risk that a project presents? 4 When would a quantitative approach be appropriate and when would you use a qualitative approach to risk assessment? Table 10.10 5 What are the benefits and limitations of the quantitative and qualitative approaches to risk Expected duration (weeks) Path Variance assessment? A 10 1.21 6 Is risk assessment the same as risk management? 8 2.00 12 1.00 7 Considering the critical path alone for the project in Table 10.9, calculate the activity variances and the total variance of the critical path. From this, calculate the standard deviation. Determine the probability of the project being completed within the following D 15 2.89 E 14 1.44 9 You are in charge of a new product launch. This will be a formal press launch, where the product is introduced by your managing director and the press and major customers have the opportunity to see the product for the first time. The formalities are to be preceded by a buffet. Before hiring the catering service it is necessary to identify the guest list and invite them to determine numbers. Because of tied arrangements between certain venues and the caterers, you will have to times: (a) 30 days. (b) 40 days. (c) 42 days. Table 10.9 Activity Optimistic time Most likely Pessimistic time time 3 4 11 select the venue, then select the caterers. The launch 1 publicity materials will need to be designed, and artwork carried out before brochures can be printed. These must be available on the day. The promotional boards to be placed around the launch room should C 10 11 8 10 18 E 1 3 F 1 3 3 4 be constructed once the publicity materials have been designed. No artwork is required for these. A sound system is required and must be hired 2 2 10 J 16 20 30 K 1 1 once the venue has been identified. Table 10.11 Activity Description Optimistic time Most likely Pessimistic time Select launch venue 1 3 Design launch publicity Have artwork prepared 2 3 4 3 D Print brochures 1 4 Construct promotion stand Order sound system E 1 2 0.5 1.5 Select caterers 1 3 Develop invite list Invite and get replies H 1 1 1 J 2 3 The activities are included in Table 10.11, together 10 Choose a project with which you are familiar. For that project, identify the opportunities that such a project presents for performance or outcome over and above what has been expected or with the best estimates for optimistic, pessimistic and most likely times. The MD has asked you to set the launch date (all times are in weeks). Show the criteria that you have used, and include the network diagram. required.
Expert Answer:
Answer rating: 100% (QA)
The possibility of suffering harm or loss There is uncertainty inherent in every plan and the variance of actual outcomes from the expected results is known as risk Risk and returns have direct relati... View the full answer
Related Book For
Posted Date:
Students also viewed these banking questions
-
A construction project requires five major pieces of work to be completed which are independent. These five paths have variances as given in Table. Determine the probability that the project will be...
-
When would a quantitative approach be appropriate and when would you use a qualitative approach to risk assessment?
-
What is risk 2 Why should risk be a fundamental part of the consideration of a project manager 3 Which other stakeholders would have an interest in the level of risk that a project presents 4 When...
-
JDBC applications are made of two models: two-tier and three-tier model. (True/False)
-
Fill in the blanks to make the following statements correct. a. A tariff imposed on the import of leather shoes will cause an ________ in the domestic price. Total quantity of leather shoes sold in...
-
Members of the Roanoke Health and Fitness Club pay an annual membership fee of $250 plus $3 each time they use the facility. Let X denote the number of times a person visits the club during the year....
-
Steven Sanchez worked as a warehouse employee for Gruma Corporation. In December 2016, Sanchez was presented an arbitration agreement during a meeting with George Tate, the human resources manager...
-
Each of the following situations involves possible violations of the AICPA's Code of Professional Conduct. For each situation, state whether it is a violation of the Code. In those cases in which it...
-
2. The benefits of financial planning Aa Aa Why Engage in Personal Financial Planning? Many people mistakenly believe that personal financial planning is an activity appropriate for only the wealthy;...
-
The Columbia River Crossing (CRC) project is in-tended to improve traffic flow in the I- 5 corridors in the greater Vancouver, Washington, and Portland, Oregon, region. The proposed project is...
-
Solve for Y(s), the Laplace transform of the solution y(t) to the initial value problem below. t, t <2 y" + 4y = g(t), y(0) = - 2, y'(0) = 0, where g(t) = 4 1, t>2 Click here to view the table of...
-
1. Discuss new technologies thatshould be implemented today and in the near future to support first responder safety practices. 2.How can the government partner with private industry to improve first...
-
Problem 1: 12 Cabins, 12 Vacancies (4 points) Bates Motel, Inc. is incorporated and headquartered in State Z. It owns and operates several hotels in several states and reports the following...
-
Locate the code of ethics online for Apple. Discuss the impact of the code of ethics on day-to-day operations for Apple? What are the costs of compliance Apple? What are the costs of non-compliance?...
-
Sometimes the governments of free market countries try to control prices to support an industry rather than the functions of supply and demand. For example, the US government supports various...
-
Analyze, and discuss the logistics services listed below and give a practical example that has been practiced in any organization/company/business. You are required to provide as many examples as you...
-
Car Park System Description GoGreen management wishes to increase security, both in their building and on site, without antagonizing their employees. They would also like to prevent people who are...
-
A statistical study shows that the fraction of television sets of a certain brand that are still in service after x years is given by f (x) = e-0.15x. (a) What fraction of the sets are still in...
-
What is the benefit to be gained from mapping a process before proceeding with the detailed planning?
-
What are the benefits and limitations of using software to help with presenting plans?
-
Time, cost and quality measured at project completion have been widely used as performance measures for projects. When might this be useful and how is this a limited approach?
-
Based on the historical record of surprises in inflation and productivity, the historical equity risk premium for the US equity market, if it is used as an estimate of the forward- looking equity...
-
Based upon Exhibit 1, the realized three-year holding period return for Novo-Gemini Inc. was closest to: A. 39.76%. B. 42.76%. C. 44.82%. Judy Chen is the primary portfolio manager of the global...
-
Based upon Exhibit 1, the expected three-year holding period return for Novo-Gemini Inc. at the time of purchase was closest to: A. 39.76%. B. 42.76%. C. 44.82%. Judy Chen is the primary portfolio...
Study smarter with the SolutionInn App