2. Which of the following is typically not a member of the Project Board? a. Technical advisor...
Fantastic news! We've Found the answer you've been seeking!
Question:
2. Which of the following is typically not a member of the Project Board?
a. Technical advisor
b. Senior user
c. Senior supplier
d. Executive/Senior Responsible Owner