3. Six Flags Great America is constructing a new roller coaster. The project is scheduled to...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
3. Six Flags Great America is constructing a new roller coaster. The project is scheduled to begin in the winter and they hope to have it ready for their busy summer season. The roller coaster planner has identified the following activities and their estimated times: Activity ABCDEFGH Immediate Predecessor A, B, C D A D, F E Time (Weeks) 3 1 245367 a) Draw the project network and compute the earliest start (ES) time, latest start (LS) time, earliest finish (EF) time and latest finish (LF) time for each activity. b) How long will it take to complete the roller coaster? c) What is the critical path? d) Compute the slack for each of the non-critical activities. e) If the planner were to add extra resources to activity F so that it takes 2 weeks instead of 3 weeks, how long would it take to complete the roller coaster? f) If the planner were to add extra resources to activity D so that it takes 3 weeks instead of 4 weeks, how long would it take to complete the roller coaster? g) A component needed to complete activity G has been damaged and a replacement has been ordered. Due to this, activity G will take eight weeks longer than originally estimated. By how many weeks will the completion of the roller coaster be delayed? 3. Six Flags Great America is constructing a new roller coaster. The project is scheduled to begin in the winter and they hope to have it ready for their busy summer season. The roller coaster planner has identified the following activities and their estimated times: Activity ABCDEFGH Immediate Predecessor A, B, C D A D, F E Time (Weeks) 3 1 245367 a) Draw the project network and compute the earliest start (ES) time, latest start (LS) time, earliest finish (EF) time and latest finish (LF) time for each activity. b) How long will it take to complete the roller coaster? c) What is the critical path? d) Compute the slack for each of the non-critical activities. e) If the planner were to add extra resources to activity F so that it takes 2 weeks instead of 3 weeks, how long would it take to complete the roller coaster? f) If the planner were to add extra resources to activity D so that it takes 3 weeks instead of 4 weeks, how long would it take to complete the roller coaster? g) A component needed to complete activity G has been damaged and a replacement has been ordered. Due to this, activity G will take eight weeks longer than originally estimated. By how many weeks will the completion of the roller coaster be delayed?
Expert Answer:
Answer rating: 100% (QA)
o draw the project network and compute the ES LS EF and LF for each activity we can use the informat... View the full answer
Related Book For
Statistics Principles And Methods
ISBN: 9780470904114
7th Edition
Authors: Richard A. Johnson, Gouri K. Bhattacharyya
Posted Date:
Students also viewed these general management questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
Which type of Organizational Model put the MOST emphasis on establishing MORALE and AUTONOMY O a. Hierarchical style Model b. O c. O d. Flat Management (Holocracy) Model Multi-divisional style Model...
-
Where can I find a sample of a cash flow statement?
-
Good Foods, Inc., is authorized to issue 5,500,000 shares of $5.00 par common stock . In its initial public offering during 2010, Good issued 475,000 shares of its $5.00 par common stock for $7.00...
-
Consider the mean square error criterion for generalized ridge regression. Show that the mean square error is minimized by choosing \(k_{j}=\sigma^{2} / \alpha_{j}^{2}, j=1\), \(2, \ldots, p\).
-
The Food Marketing Institute shows that 17% of households spend more than $100 per week on groceries. Assume the population proportion is p = .17 and a sample of 800 households will be selected from...
-
[1] In Calculus, it can be proven that Write a MATLAB script that approximates this infinite series by a finite such that the absolute error falls below a certain tolerance entered by the user. For...
-
Marider Industries makes two types of windbreaker jackets: one for spring and one for winter. Marider uses a traditional costing system and is considering switching to an Activity-Based Costing...
-
What was the type of malware to which the company fell victim? Briefly summarize the malware attack. Did the company have a cybersecurity strategy prior to the attack? If so, was it effective? What...
-
If the level of foreign incomes decreases, what would happen to the demand for the Canadian dollar? Question 1 options: a) The demand for Canadian dollars would decrease b) The demand for Canadian...
-
If new, better picking and transportation tools become available for a higher rent, and if Johns decides to lease them, how will this affect John's ATC, AVC, and MC curves? Consider that in addition...
-
star is travelling at 0 . 6 c towards planet earth. It explodes. a ) At what speed is the light from the explosion travelling as measured relative to the star? b ) At what speed is the light from the...
-
Which x - ray photon in a characteristic cascade is considered diagnostic?
-
Is Top management involvement in setting health and safety policies is essential for avoiding setting an example of inaction?
-
The Holt fund has $632 million in assets, 47 million in debt and 18 million shares at the start of the year. At the end of the year, the fund has $750 million in assets, 37 million in debt and 20...
-
Imagine that your best friend knows you are taking a psychology course and wonders what psychology is all about. How would you define psychology for your friend? Write an essay on the discipline of...
-
Refer to Exercise 2.27 and the data on the consumer price index for various cities. Find the increase, for each city, by subtracting the 2007 value from the 2011 value. (a) Find the sample mean and...
-
Identify the variable as a discrete or a continuous random variable in parts (a)-(e). (a) The loss of weight following a diet program. (b) The magnitude of an earthquake as measured on the open-ended...
-
Consider the following setting of a random selection: A box contains 100 cards, of which 25 are numbered 1, 35 are numbered 2, 30 are numbered 3, 10 are numbered 4. One card will be drawn from the...
-
Data were collected to discern environmental factors affecting health standards. For 21 small regions we have data on the following variables: The data are given in Table 8.27. (a) Perform a...
-
We have data on the distance covered by irrigation water in a furrow of a field. The data are to be used to relate the distance covered to the time since watering began. The data are given in Table...
-
In this problem we are trying to estimate the survival of liver transplant patients using information on the patients collected before the operation. The variables are: The data are given in Table...
Study smarter with the SolutionInn App