4 16-2. The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
4 16-2. The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below. At the present time, the inventories of parts and lead times are as follows: Chair Leg Back assembly assembly Rails Legs Top Spindles (4) (4) (4) MPS Week: Chair, LT = 1 Gross Requirements a. Develop a materials plan for all the parts. 1 2 Week: Scheduled Receipts Projects available Net Requirements Planned Order Releases Chairs Seat Leg assem Back assem Seat 0 Rails Legs Top Spindles 1 0 AL The company would like to produce 600 chairs in week 5 and 300 chairs in week 6. 0 On Hand 100 0 0 8 00 40 3 150 30 80 0 50 25 100 3 4 600 300 0 100 100 100 100 100 LT (wks) 1 4 5 0 600 0 0 0 0 0 500 300 6 300 3 5 6 7 8 0 122 0 500 300 0 2 1 1 7 8 9 9 Leg assem, LT₁=2 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases Week: Back assem, LT 1 Week: Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases Seat, LT= 3 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases 0 Week: 0 Rails (4), LT-1 Week: Gross Requirements H 0 '0 1 0 0 10 50 50 3 4 5 500 300 0 0 50 50 0 ¹0 450 300 0 0 2 0 0 0 0 450 300 0 2 0 10 25 25 0 '0 '0 0 0 2 3 0 0 0 25 25 0 0 475 300 475 300 0 460 300 4 5 500 300 3 0 0 0 40 40 40 40 0 0 460 300 00 1 2 3 0 1800 1200 4 5 500 300 0 4 0 0 0 0 5 0 0 6 0 0 0 6 0 0 0 0 0 0 0 0 0 6 0 0 0 6 0 7 7 7 7 8 9 8 9 8 9 8 9 Scheduled Receipts Projects available Net Requirements Planned Order Releases Legs (4), LT=₁1 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases 0 0 100 100 0 1700 1200 1700 1200 Week: 1 0 Top, LT=2 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases Week: Spindles (4), LT=2 Week: Gross Requirements 0 10 150 150 0 1650 1200 1650 1200 0 0 2 0 0 0 0 0 2 3 4 1800 1200 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 3 4 1900 1200 0 0 0 0 3 4 0475 300 0 0 10 0 0 0 30 30 30 0 0 0 445 300 445 300 0 00 0 0 0 5 5 0 0 0 0 0 0 0 5 00 0 6 0 0 0 00 6 7 7 6 7 8 8 8 9 9 Scheduled Receipts On-Hand Balance Net Requirements Planned Order Releases 0 00 0 80 80 80 0 00 1820 1200 1820 1200 0 0 0 0 Workload Week: Backs Assembly hours 0 0 0 0 b. What actions should be taken now? We should be ordered immediately 460 seats, 1700 rails, 1650 legs, 445 tops, 1820 spindles 0 0 c. Assume it takes one hour to assemble backs, one hour to assemble legs, and two hours to finish complete chairs. Total assembly time for all three types of assembly is limited to 1,000 hours per week. Will this capacity constraint cause a bottleneck in assembly (Use original material requirements plan)? If it does, what can be done? 0 The 1000-hour capacity limit in assembly will cause problems in week 4, since the assembly time required to meet the plan is 1300 hours. Possible solutions include overtime, splitting lots so that some work is done in week 3 or 5 instead, or smoothing the master schedule so that there aren't so many assembly hours required during week 4. 2 31 4 5 0 475 300 0 6 7 8 9 0 LegsAssembly Finish Chairs Assembly 0 Total Assembly 0 0 450 300 00 0 1000600 0 0 450 775 1300 600 0 0 d. What is the effect of changing the master schedule to 300 chairs in week 5 and 400 chairs in week 6? Using the assumptions in part(c) balances the assembly hours required so that now 150 hours are required in week 2, 575 in week 3, and 800 each in weeks 4 and 5. This plan would solve the problem in week 4 in assembly. E. Assume the 80 spindles in stock could not be located anywhere in the company. 1. What changes would occur to the plan 2. What actions would be needed? 4 16-2. The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below. At the present time, the inventories of parts and lead times are as follows: Chair Leg Back assembly assembly Rails Legs Top Spindles (4) (4) (4) MPS Week: Chair, LT = 1 Gross Requirements a. Develop a materials plan for all the parts. 1 2 Week: Scheduled Receipts Projects available Net Requirements Planned Order Releases Chairs Seat Leg assem Back assem Seat 0 Rails Legs Top Spindles 1 0 AL The company would like to produce 600 chairs in week 5 and 300 chairs in week 6. 0 On Hand 100 0 0 8 00 40 3 150 30 80 0 50 25 100 3 4 600 300 0 100 100 100 100 100 LT (wks) 1 4 5 0 600 0 0 0 0 0 500 300 6 300 3 5 6 7 8 0 122 0 500 300 0 2 1 1 7 8 9 9 Leg assem, LT₁=2 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases Week: Back assem, LT 1 Week: Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases Seat, LT= 3 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases 0 Week: 0 Rails (4), LT-1 Week: Gross Requirements H 0 '0 1 0 0 10 50 50 3 4 5 500 300 0 0 50 50 0 ¹0 450 300 0 0 2 0 0 0 0 450 300 0 2 0 10 25 25 0 '0 '0 0 0 2 3 0 0 0 25 25 0 0 475 300 475 300 0 460 300 4 5 500 300 3 0 0 0 40 40 40 40 0 0 460 300 00 1 2 3 0 1800 1200 4 5 500 300 0 4 0 0 0 0 5 0 0 6 0 0 0 6 0 0 0 0 0 0 0 0 0 6 0 0 0 6 0 7 7 7 7 8 9 8 9 8 9 8 9 Scheduled Receipts Projects available Net Requirements Planned Order Releases Legs (4), LT=₁1 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases 0 0 100 100 0 1700 1200 1700 1200 Week: 1 0 Top, LT=2 Gross Requirements Scheduled Receipts Projects available Net Requirements Planned Order Releases Week: Spindles (4), LT=2 Week: Gross Requirements 0 10 150 150 0 1650 1200 1650 1200 0 0 2 0 0 0 0 0 2 3 4 1800 1200 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 3 4 1900 1200 0 0 0 0 3 4 0475 300 0 0 10 0 0 0 30 30 30 0 0 0 445 300 445 300 0 00 0 0 0 5 5 0 0 0 0 0 0 0 5 00 0 6 0 0 0 00 6 7 7 6 7 8 8 8 9 9 Scheduled Receipts On-Hand Balance Net Requirements Planned Order Releases 0 00 0 80 80 80 0 00 1820 1200 1820 1200 0 0 0 0 Workload Week: Backs Assembly hours 0 0 0 0 b. What actions should be taken now? We should be ordered immediately 460 seats, 1700 rails, 1650 legs, 445 tops, 1820 spindles 0 0 c. Assume it takes one hour to assemble backs, one hour to assemble legs, and two hours to finish complete chairs. Total assembly time for all three types of assembly is limited to 1,000 hours per week. Will this capacity constraint cause a bottleneck in assembly (Use original material requirements plan)? If it does, what can be done? 0 The 1000-hour capacity limit in assembly will cause problems in week 4, since the assembly time required to meet the plan is 1300 hours. Possible solutions include overtime, splitting lots so that some work is done in week 3 or 5 instead, or smoothing the master schedule so that there aren't so many assembly hours required during week 4. 2 31 4 5 0 475 300 0 6 7 8 9 0 LegsAssembly Finish Chairs Assembly 0 Total Assembly 0 0 450 300 00 0 1000600 0 0 450 775 1300 600 0 0 d. What is the effect of changing the master schedule to 300 chairs in week 5 and 400 chairs in week 6? Using the assumptions in part(c) balances the assembly hours required so that now 150 hours are required in week 2, 575 in week 3, and 800 each in weeks 4 and 5. This plan would solve the problem in week 4 in assembly. E. Assume the 80 spindles in stock could not be located anywhere in the company. 1. What changes would occur to the plan 2. What actions would be needed?
Expert Answer:
Answer rating: 100% (QA)
a The materials plan for all parts is shown low alrs Gross Requirements Onh... View the full answer
Related Book For
Operations Management in the Supply Chain Decisions and Cases
ISBN: 978-0073525242
6th edition
Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein
Posted Date:
Students also viewed these mathematics questions
-
The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below. At the present time, the inventories of parts and lead times are as follows: The firm would like to produce...
-
A small furniture maker has just received an order to deliver 250 chairs at the beginning of week 6. The production/purchase planner needs to arrange for the assembly of subassemblies and purchase of...
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
A chef in a restaurant that specializes in pasta dishes was experiencing difficulty in getting brands of pasta to be al dente-that is, cooked enough so as not to feel starchy or hard but still feel...
-
Yan Corp. had the following stock issued and outstanding at January 1, 2013: 1. 60,000 shares of no-par common stock. 2. 15,000 shares of $100 par, 4 percent, cumulative preferred stock. (Dividends...
-
For each of the following, compute (i) det(A), (ii) adj A, and (iii) A-1. (a) (b) 2 110 100
-
The adjusted trial balance for Spruce Up Catering, Inc., is presented next. Prepare the income statement, statement of retained earnings, and balance sheet for Spruce Up Catering, Inc., for the month...
-
Lets be more practical. DCF is not the gospel. Managers should not become so enchanted with DCF that strategic considerations are overlooked. Do you agree? Explain.
-
Harris Company manufactures and sells a single product. A partially completed schedule of the company's total costs and costs per unit over the relevant range of 60,000 to 100,000 units is given...
-
The trial balance of Telegraphic Link at November 30, follows: Additional information at November 30, 2012: a. Accrued service revenue, $600. b. Depreciation, $300. c. Accrued salary expense, $800....
-
Lancaster Company had earnings net of tax but before extraordinary items of $ 5 0 0 , 0 0 0 . They had an extraordinary loss net of tax of $ 1 0 0 , 0 0 0 . Lancaster had a weighted average number of...
-
a. Define inherent risk. b. When might an auditor choose to forego assessing inherent risk for an assertion?
-
a. Define materiality at the account-balance level. b. What is another name for materiality at this level? c. Distinguish between the terms material account balance and materiality.
-
a. What official quantitative guidelines exist for financial statement materiality? b. State five quantitative guidelines commonly used in practice.
-
State the two levels at which preliminary judgments of materiality should be made in the planning phase and state the reason for each.
-
a. What is a preliminary audit strategy? b. Name two alternative audit strategies.
-
All of the following are true regarding the California Earned Income Tax Credit (CalEITC) except: A. The CalEITC is refundable B. The taxpayer, his or her spouse, and any qualifying children must...
-
Prove the formula for (d/dx)(cos-1x) by the same method as for (d/dx)(sin-1x).
-
Valley View Hospital faces somewhat seasonal demand. Patients defer elective surgery in the summer and in the holiday season at the end of the year. As a result, the forecast of patient days of...
-
How can lean and Six Sigma approaches work together in making process improvements?
-
Compare the Baldrige-based approach to the use of ISO 9000.
-
If debentures are included as part of capital employed, what figure is used for return? How and why does it differ from the return figure used for calculating return on ordinary shareholders capital...
-
What information (in addition to the current ratio, quick ratio, capital gearing ratio and interest times cover) would you want to assess a companys solvency?
-
How could a company increase its profitability when sales are falling (assuming that it is unable to increase sales)?
Study smarter with the SolutionInn App