6.43 Utama Computer is planning to design, manufacture and market the UCI palm-book. The project manager...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
6.43 Utama Computer is planning to design, manufacture and market the UCI palm-book. The project manager has listed the major activities that must be completed. The activities, times and costs are given below. Activity ABCDEFGHIKL Immediate Predecessor Time (months) Cost ($'000) Normal Crash Normal Crash B A, D C E, G E, G E, G 956625654653 534 10 12 9.2 4 11 11.6 1 4 3 3 4 3 1 46876696 5.3 7.4 10 8 8 10 9 8.6 H J. F (a) Using the normal times, construct a network for the project and identify all critical activities. (Ans: BDEHK) (b) Determine the project completion time and the total cost based on normal times. (Ans: 23 months, $87000) (c) Find the minimum cost required to complete the project within 20 months. (Ans: $89600) 6.44 The following table provides the data (activities, immediate predecessors, and durations) for building a new house. (a) Construct a network diagram, and state the critical path and the duration of the project. (Ans: ACDFGHJLNST, 38 days) (b) Assuming each activity starts at its earliest time, construct the time schedule (time chart) for the project. 6.43 Utama Computer is planning to design, manufacture and market the UCI palm-book. The project manager has listed the major activities that must be completed. The activities, times and costs are given below. Activity ABCDEFGHIKL Immediate Predecessor Time (months) Cost ($'000) Normal Crash Normal Crash B A, D C E, G E, G E, G 956625654653 534 10 12 9.2 4 11 11.6 1 4 3 3 4 3 1 46876696 5.3 7.4 10 8 8 10 9 8.6 H J. F (a) Using the normal times, construct a network for the project and identify all critical activities. (Ans: BDEHK) (b) Determine the project completion time and the total cost based on normal times. (Ans: 23 months, $87000) (c) Find the minimum cost required to complete the project within 20 months. (Ans: $89600) 6.44 The following table provides the data (activities, immediate predecessors, and durations) for building a new house. (a) Construct a network diagram, and state the critical path and the duration of the project. (Ans: ACDFGHJLNST, 38 days) (b) Assuming each activity starts at its earliest time, construct the time schedule (time chart) for the project.
Expert Answer:
Related Book For
Quantitative Analysis for Management
ISBN: 978-0132149112
11th Edition
Authors: Barry render, Ralph m. stair, Michael e. Hanna
Posted Date:
Students also viewed these mathematics questions
-
Homework-2 DECISION ANALYSIS PROBLEMS Problem-1: Kenneth Brown is the principal owner of Brown Oil, Inc. After quitting his university teaching job, Ken has been able to increase his annual salary by...
-
answer all questions as instructed below. attend all questions. 4 Computer Vision (a) Explain why such a tiny number of 2D Gabor wavelets as shown in this sequence are so efficient at representing...
-
Rice and Flower were partners sharing profit and loss equally. Statement of Financial Position as at 31 December 2020. Non current Assets Premises Machinery Vehicles Fittings Current Assets Inventory...
-
Here are four different joint PMFs: (a) For each pair of random variables, indicate whether the two random variables are independent, and compute the correlation coefficient p. (b) Compute the least...
-
During the audit of a dealership selling only new luxury automobiles, the auditors calculated the year 2 and year 1 ratios in the table below. Select the most reasonable explanation the controller...
-
Pluto Corporation issued \(\$ 400,000\) of \(7 \%, 20\) year bonds payable on March 31, 2006. The bonds were issued at 100 and pay interest on March 31 and September 30. Record (a) issuance of the...
-
Valuing a right Knight inventory Systems, Inc., has announced a rights offer. The company has announced that it will take four rights to buy a new share in the offering at a subscription price of...
-
Case Study # 1: Tech Covers Inc Production Planning (Total marks: 25) "Tech Covers Inc." is a company that produces covers for three types of devices: laptops, tablets, and smartphones. The company's...
-
A process is in statistical control with x = 199 and R = 3.5. The control chart uses a sample size of n= 4. Specifications are at 200 ± 8. The quality characteristic is normally distributed....
-
The following table shows the time data run at different temperatures as described in Step 5 of the experimental procedure. Copy the concentration data from Reaction Mixture 1 above, and calculate...
-
Explain the role of investment bankers.
-
Proponents of tax simplification argue that a flat tax would be fairer. In what ways is this true? In what ways would a flat tax be less fair?
-
Determine a fund's net asset value.
-
Contrast the various money market instruments.
-
As a manager or leader, what steps would you take, if any, to educate your employees about interpersonal communication?
-
Use the confidence interval to find the margin of error and the sample mean. (1.49,1.97) The margin of error is (Round to two decimal places as needed.)
-
Chapter 9 Stock Valuation at Ragan Engines Input area: Shares owned by each sibling Ragan EPS Dividend to each sibling Ragan ROE Ragan required return Blue Ribband Motors Corp. Bon Voyage Marine,...
-
Because of a sluggish economy, Bechtold Construction has been forced to modify its plans for the housing development in Problem 11-9. The result is that the path from node 6 to 7 now has a distance...
-
Trowbridge Manufacturing produces cases for personal computers and other electronic equipment. The quality control inspector for this company believes that a particular process is out of control....
-
Resolve Problem 15-12 (Goodeating Dog Chow) for five periods.
-
For a gas, if enthalpy is considered to be the function of temperature and pressure, then show that the Joule-Thomson coefficient is \[ \mu_{\mathrm{JT}}=-\frac{1}{C_{P}}\left(\frac{\partial...
-
What is inversion temperature? Mention the importance of this temperature in explaining the heating or cooling effect of a gas with the help of the Joule-Thomson inversion curve.
-
6.17 Show that P
Study smarter with the SolutionInn App