A bar chart schedule for a project is shown below along with the estimated cost for...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A bar chart schedule for a project is shown below along with the estimated cost for each activity. The schedule shows the planned timing and duration of the activities at the start of the project. The costs are also estimated at the beginning of the project, and incurred at a constant rate across the duration of the activities. Estimated Time (days) 7 Activity Total Cost 1 2 3 4 5 6 8 9 10 11 12 $700 $1,600 $820 $330 $700 $1,800 $240 $300 $200 $450 $570 $200 $120 Total $8,030 The work begins as scheduled, and after five days of work on the project, a progress report shows the following information about the percent complete and actual costs of each activity: % Complete at end Actual Cost of Activity of 5 days Work to Date A 100% $700 B 75% $1,300 C 50% $400 D 100% $310 E 20% $150 F 0% $0. G 60% $200 H 0% SO I 0% $0 J 60% $375 K 0% $0 L 0% SO M 0% $0 Use the information provided above and Earned Value concepts to answer the following questions: ABCDEFGH 1 K L M a. Draw a cost profile (cumulative cost curve with time on horizontal axis and $ on vertical axis) showing the cumulative project cost over the course of the project for the as- planned condition with estimated costs. b. What is the status of the project in terms of schedule (ahead or behind)? Check SV and SPI. d. c. What is the status of the project in terms of budget (over or under)? Check CV and CPI. What is the estimated total cost of completing all of the work (EAC)? Assume the CPI will remain the same for the remainder of the project. e. What is the expected cost to complete all of the remaining project work (ETC) assuming the work is proceeding as planned? f. Using variance at completion (VAC), determine whether the project is expected to be over or under budget at completion of the project? g. Based on the efficiency that must be maintained in order to complete the current EAC, will it be harder, easier, or the same level of effort to complete the work? Use the "To Complete Performance Index" (TCPI). A bar chart schedule for a project is shown below along with the estimated cost for each activity. The schedule shows the planned timing and duration of the activities at the start of the project. The costs are also estimated at the beginning of the project, and incurred at a constant rate across the duration of the activities. Estimated Time (days) 7 Activity Total Cost 1 2 3 4 5 6 8 9 10 11 12 $700 $1,600 $820 $330 $700 $1,800 $240 $300 $200 $450 $570 $200 $120 Total $8,030 The work begins as scheduled, and after five days of work on the project, a progress report shows the following information about the percent complete and actual costs of each activity: % Complete at end Actual Cost of Activity of 5 days Work to Date A 100% $700 B 75% $1,300 C 50% $400 D 100% $310 E 20% $150 F 0% $0. G 60% $200 H 0% SO I 0% $0 J 60% $375 K 0% $0 L 0% SO M 0% $0 Use the information provided above and Earned Value concepts to answer the following questions: ABCDEFGH 1 K L M a. Draw a cost profile (cumulative cost curve with time on horizontal axis and $ on vertical axis) showing the cumulative project cost over the course of the project for the as- planned condition with estimated costs. b. What is the status of the project in terms of schedule (ahead or behind)? Check SV and SPI. d. c. What is the status of the project in terms of budget (over or under)? Check CV and CPI. What is the estimated total cost of completing all of the work (EAC)? Assume the CPI will remain the same for the remainder of the project. e. What is the expected cost to complete all of the remaining project work (ETC) assuming the work is proceeding as planned? f. Using variance at completion (VAC), determine whether the project is expected to be over or under budget at completion of the project? g. Based on the efficiency that must be maintained in order to complete the current EAC, will it be harder, easier, or the same level of effort to complete the work? Use the "To Complete Performance Index" (TCPI).
Expert Answer:
Answer rating: 100% (QA)
a Cost profile See graph on next page Budgeted at completion BAC for all activities 1745 After 4 wee... View the full answer
Related Book For
Posted Date:
Students also viewed these organizational behavior questions
-
1. Question 1: Make following hierarchy structure of directories. Java is file. Create it in Section 2 And copy in Section 1 and Section 3 2. Use different options of directory and file commands of...
-
Develop a linear regression model: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 A Year 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007...
-
A 1 defects size B D E 88888888888888888888888888 2 21 3 24 4 16 5 12 6 15 7 5 8 28 9 20 10 31 11 25 12 20 13 24 14 16 15 19 16 10 17 17 18 13 19 22 20 18 21 39 22 30 23 24 24 16 25 19 26 17 27 15...
-
Calculate the weighted average cost of capital for Genedak-Hogan for before and after international diversification. Did the reduction in debt costs reduce the firm's weighted average cost of...
-
Carla Company uses the perpetual inventory system. The following information is available for January of the current year, when Carla Company sold 1,600 units of inventory on January 14. Using the...
-
(A) Using the price-demand function p(x)=2,000 - 60x 1 x 25 from Problem 88, write the company's revenue function and indicate its domain. (B) Complete Table 11, computing revenues to the nearest...
-
What is the Fickian diffusivity of chlorobenzene in liquid bromobenzene at \(300 \mathrm{~K}\) when the mole fraction of chlorobenzene is 0.0332 ? Assume that the diffusivity follows an Arrhenius...
-
Karen has filed a voluntary petition for a Chapter 7 proceeding. The total value of her estate is $35,000. Ben, who is owed $18,000, has a security interest in property valued at $12,000. Lauren has...
-
Book Differential Analysis for Machine Replacement Ridgeway Digital Components Company assembles circuit boards by using a manually operated machine to insert electronic components. The original cost...
-
Soo Office Equipment manufactures and sells metal shelving. It began operations on January 1, 2013. Costs incurred for 2013 are as follows (V stands for variable; F stands for fixed): Direct...
-
x y z Consider the following circuit: 40 Figure: Problem 3. (a) Write down the functional output F(x, y, z) without any simplification. (b) Algebraically minimise and implement F(x, y, z) in its sum...
-
What specific circumstances and evidence led the doctor to discharge the staff member who had worked for him for nine months, and how does the doctor respond to the staff member's claim of age...
-
Follow the link to the excel sheet with tabs labeled P&L and 6-month plan. This is for a project where I partnered Nike with the video game Fortnite. They will have a collaboration where they will...
-
Problem 1 (Day Sales Outstanding) Tulips Company has a DSO of 40 days, and its annual sales are P7, 300, 000. What is its accounts receivable balance? Assume that it uses a 363-day year. Problem 2...
-
To reduce the inherent risk of global operations and gain market access and market expertise, what do companies often rely on? Explain.
-
You are planning to renew your car in eight years from now. The new car is expected to cost $50,000 and you believe that your old car would sell for $10,000 at that time. If you are going to make...
-
A cartoon company is looking to migrate their long running on premise batch aplication to run on EC 2 instances.They want to ensures optimal cost usage while implementing the same.The application to...
-
What services are provided by the provincial and territorial governments?
-
Cavanaugh Construction specializes in designing and building custom homes. Business has been excellent, and Cavanaugh projects a 10% growth rate for the foreseeable future. The company just paid a...
-
Reconsider the Connecticut Computer Company of the previous problem assuming the firm has experienced some difficulties and its EBIT has fallen to $8,000. a. Reconstruct the three-column chart...
-
Should the project being considered in the previous problem be accepted or rejected based on IRR? (Hint: Start by guessing 11% for IRR.)
-
The Arcadia Company is contemplating a large capital investment of \($32\) million in new productionline equipment, which is expected to have a useful life of six years, a residual value of \($2\)...
-
San Joaquin Company began exploration of oil in Texas by paying \($600,000\) for the drilling rights on a large tract of land. The company drilled 10 oil wells on the land. Seven of the wells were...
-
The Arcadia Company is contemplating a large capital investment of \($32\) million in new productionline equipment, which is expected to have a useful life of six years and a residual value of \($2\)...
Study smarter with the SolutionInn App