A contractor plans to use a wheeled loader to move 5,000 BCY of soil 500 feet using
Fantastic news! We've Found the answer you've been seeking!
Question:
A contractor plans to use a wheeled loader to move 5,000 BCY of soil 500 feet using a 50-minute working hour. The soil has a swell of 15%. The loader has a bucket capacity of 2.5 cubic yards. The soil has a fill factor of 1.2 and a weight of 2,500 lbs per LCY. The loader has an STL of 50% of 15,000 lbs. The loader will haul in one direction loaded at 2.5 miles per hour and return at 3.5 miles per hour. The total cost of the tractor is $55.00 per hour. It has a fixed time of .35 minutes. Remember that the loader will be moving the dirt in its loose state.
What is the productivity of the loader in LCY per hour?
Related Book For
An Introduction to Geotechnical Engineering
ISBN: 978-0132496346
2nd edition
Authors: Robert D. Holtz, William D. Kovacs, Thomas C. Sheahan
Posted Date: