a) If job-1 is placed into the 4th order, find all feasible schedules considering the dominance conditions.
Fantastic news! We've Found the answer you've been seeking!
Question:
a) If job-1 is placed into the 4th order, find all feasible schedules considering the dominance conditions.
b) For all schedules in part (a) compute the objective values and find the best schedule. Can we say that the best schedule also must be an optimal schedule?