A manufacturing facility needs to open a new assembly line in four months or there will be
Fantastic news! We've Found the answer you've been seeking!
Question:
(1) Find the probability distribution of X. (Use appropriate mathematical expressions wherever you can to answer this question.) (2 points)
(2) What is the probability that this project will be completed in at least 3 months from now? (2 points)
(3) What is the probability that this project will not be completed on time? (2 points)
(4) What is the expected completion time (in months) from now for this project? (3 points)
(5) How much variability (in months) exists around the expected value found in question (4)? Give both the variance and standard deviation.