A project is calculated to have a critical path duration of 10 days with 3 activities on
Fantastic news! We've Found the answer you've been seeking!
Question:
A project is calculated to have a critical path duration of 10 days with 3 activities on the critical path and corresponding standard deviations A (standard deviation is 2) B (standard deviation is 1) and C (standard deviation is 2). What is the probability the project will take more than 16 days to finish?