A project schedule is developed by estimating the duration of each of the activities defined in
Question:
A project schedule is developed by estimating the duration of each of the activities defined in the Work Breakdown Structure. A Gantt Chart is a graphical representation of the project schedule that shows, among other things, the project’s critical path. Activities on the critical path are those that, if delayed, will impact the project finish date. A Network Diagram is another graphical representation of the project schedule. It depicts the relationships among the project activities.
QUESTION: How do construct a Gantt Chart and a Network Diagram with the information provided on the belo Work Breakdown Structure (WBS) along with the case study information highlighted below?
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray