A quality characteristic is monitored by a control chart designed so the probability that a certain out-of-control
Fantastic news! We've Found the answer you've been seeking!
Question:
A quality characteristic is monitored by a control chart designed so the probability that a certain out-of-control condition will be detected on the first sample following the shift to that state is 1 − β. Find the following: (a) The probability that the out-of-control condition will be detected on the second sample following the shift. (b) The probability that the out-of-control condition will be detected on the mth sample following the shift. (c) The probability that the shift is still not detected on the mth subsequent sample. (d) The probability that two consecutive samples produce statistics that plot outside the control limits
Related Book For
Introduction to Statistical Quality Control
ISBN: 978-1118146811
7th edition
Authors: Douglas C Montgomery
Posted Date: