A restaurant conducted a time study for a job assembling ham and cheese sandwiches. There were 10
Fantastic news! We've Found the answer you've been seeking!
Question:
A restaurant conducted a time study for a job assembling ham and cheese sandwiches. There were 10 cycles on the job and the average time was recorded to be 0.385 minutes. Determine the standard time of the assembly if the operator is rated 80% and the allowance factor is 12%.