A shop owner uses a reorder point approach to restocking a certain raw material. Lead time is
Fantastic news! We've Found the answer you've been seeking!
Question:
A shop owner uses a reorder point approach to restocking a certain raw material. Lead time is 6 days. Usage of the material is normally distributed with a mean of 80 pounds per day and a standard deviation of 6 pounds. When should the raw material be reordered if the acceptable risk of a stockout is 4% (Customer service level is 96%)?