A toy company needs to calculate material requirements for its top-selling toy car. The graphic aboveshows the
Question:
A toy company needs to calculate material requirements for its top-selling toy car. The graphic aboveshows the bill of material for this item. Below arethree MRP tables for the top-level assembly (the car) and some of its components:
Toy Car Final Assembly | 8/3 | 8/10 | 8/17 | 8/24 | 8/31 | 9/7 | 9/14 | 9/21 | 9/28 | |
Gross Requirements | 800 | 900 | 2100 | 2500 | ||||||
Scheduled Receipts | 440 | 550 | 320 | |||||||
Projected On-Hand Inv. | 110 | |||||||||
Net Requirements | ||||||||||
Planned Order Receipts | ||||||||||
Planned Order Releases | ||||||||||
Lead Time (in weeks) | 1 | |||||||||
Lot Size | 70 |
Wheel Assembly | 8/3 | 8/10 | 8/17 | 8/24 | 8/31 | 9/7 | 9/14 | 9/21 | 9/28 | |
Gross Requirements | ||||||||||
Scheduled Receipts | 1600 | 1900 | 2200 | |||||||
Projected On-Hand Inv. | 400 | |||||||||
Net Requirements | ||||||||||
Planned Order Receipts | ||||||||||
Planned Order Releases | ||||||||||
Lead Time (in weeks) | 1 | |||||||||
Lot Size | 100 |
Axle | 8/3 | 8/10 | 8/17 | 8/24 | 8/31 | 9/7 | 9/14 | 9/21 | 9/28 | |
Gross Requirements | ||||||||||
Scheduled Receipts | 800 | 1900 | ||||||||
Projected On-Hand Inv. | 700 | |||||||||
Net Requirements | ||||||||||
Planned Order Receipts | ||||||||||
Planned Order Releases | ||||||||||
Lead Time (in weeks) | 4 | |||||||||
Lot Size | 200 |
For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31?
For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? For the Axle table above, what are the Gross Requirements in the week of 9/7? For the Axle table above, what are the Gross Requirements in the week of 9/14? For the Axle table above, what are the Planned Order Releases in the week of 8/17?