According to the cost of funded risk retention, the data for Astaka Berhad.are as follow : The
Fantastic news! We've Found the answer you've been seeking!
Question:
According to the cost of funded risk retention, the data for Astaka Berhad.are as follow :
The property value is RM2,000,000 and the expected loss for the property is RM40,000.The maximum loss for the property similar as the property value and the risk was RM980,000. If the investment return of the company was 16%, and the bank interest was 8%.
You are required to calculate :
i Cost of financing loss
ii Cost of financing risk
iii Cost of retention