Acme is planning construction of a new loading ramp for its single iron mill. The initial cost
Fantastic news! We've Found the answer you've been seeking!
Question:
Acme is planning construction of a new loading ramp for its single iron mill. The initial cost of the investment is $1 million. Efficiencies from the new ramp are expected to reduce costs by $100,000 for the life of the plant which is currently estimated at another 30 years. The $100,000 cost savings is per year for the 30 year life of the project. When will this project break-even on a discounted cash basis if the discount rate is 10%?