Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E?
Activity | Expected Activity Time | ES | EF | LF |
A | 5 | 0 | ||
B | 18 | 5 | ||
C | 13 | 5 | ||
D | 3 | 23 | ||
E | 10 | 23 | ||
F | 4 | 33 | 46 | |
G | 11 | 44 |