Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity | Event | Immediate Predecessor(s) | Estimates of Activity Duration (Weeks) | |||
Optimistic (To) | Most Likely (Tm) | Pessimistic (Tp) | Average (Te) | |||
1 | A | - | 2 | 3 | 4 | ? |
2 | B | A | 1 | 2 | ? | 2 |
3 | C | A | 1 | ? | 4 | 2.2 |
4 | D | B | ? | 5 | 6 | 5 |
5 | E | B | 3 | ? | 5 | 4 |
6 | F | C | 2 | 3 | ? | 3 |
7 | G | D | ? | 2 | 4 | 2.2 |
8 | H | E,F, G | 3 | 4 | 6 | ? |
9 | I | H | 3 | ? | 5 | 4 |
10 | J | I | 2 | 1 | 3 | ? |
Questions:
Calculate ALL the missing (?) data points.