Activity Predecessor Normal Duration Normal Cost Crash Time Crash Cost A -- 4 200 3 900 B
No answer yet for this question.
Ask a Tutor
Question:
Draw the AON network diagram
Find the Critical Path
What is the Critical Time
What is the Float of B
What is the normal cost of the project
Crash the project till project duration (CT) reaches 10 days, what is the critical path and the crash costs for the project