a. Draw a project network. (No Handwritten assignments accepted) Activity
Fantastic news! We've Found the answer you've been seeking!
Question:
a. Draw a project network. (No Handwritten assignments accepted)
Activity | Predecessor(s) | Normal Time (Wks) | Crash Time (Wks) | Normal Cost | Crash Cost | |
A | --- | 5 | 4 | $400 | $750 | |
B | A | 8 | 6 | 1600 | 2200 | |
C | A | 7 | 6 | 800 | 1100 | |
D | -- | 6 | 5 | 600 | 1000 | |
E | B,D,C | 8 | 6 | 1200 | 2200 | |
F | D | 3 | 2 | 800 | 1000 | |
G | D | 3 | 2 | 500 | 650 | |
H | E | 4 | 3 | 400 | 600 | |
I | F,G,H | 6 | 5 | 900 | 1300 |
b. What is the critical path?
c. What is the normal project cost?
d. What is the total cost of the project if you need to crash it by 1 week?
Related Book For
Essentials Of Statistics For The Behavioral Sciences
ISBN: 9781133956570
8th Edition
Authors: Frederick J Gravetter, Larry B. Wallnau
Posted Date: