Activity Q on a project has exactly 4 successors E, F, G, and H whose late start
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity Q on a project has exactly 4 successors E, F, G, and H whose late start days are 20, 12, 38, and 32. (Here "day" means days after project start and successor in this context means that E, F, G, and H are all dependent on Q.) What is the late finish day of Q?