Afeeya Faeeqa AOR Bakery is planning to produce a new line of cake. The management has designated
Fantastic news! We've Found the answer you've been seeking!
Question:
Afeeya Faeeqa AOR Bakery is planning to produce a new line of cake. The management has designated an output rate of 40 units per day. The company's operations time is from 9.00 a.m. until 5.00 p.m. in a day and the productive time per hour at 55 minutes. The tasks involved are as follows:
assignment/ Task | follow/ Predecessors | Assignment Time/ Task Time (Minutes) |
A | - | 10 |
B | A | 11 |
C | B | 5 |
D | B | 4 |
AND | A | 10 |
F | C, D | 2 |
G | F | 7 |
H | AND | 11 |
I | G, H | 3 |
a) Calculate the cycle time for this operation (minutes/unit).
b) Compute the total task time (minutes).
c) Compute the theoretical minimum number of workstations
d)What is the actual number of workstations?
e) What is the largest cyle time (minutes)?
d) What is the percentage of the line efficiency?