M/s Motwani limited have taken up a special project consisting of 10 activities whose three-point time estimates are listed in the table below. Activities are marked with their node numbers.
1-2 1 2 3 1-3 1 2 3 1-4 1 2 3
Activity
Time Estimates in weeks
Optimistic
Most Likely
Pessimistic
Internal Assignment Applicable for September 2022 Examination
2-5 4 9 20 3-5 2 5 14 3-7 3 6 15 5-7 1 2 9 4-6 2 4 6 6-7 3 3 3 7-8 4 4 4
1. Find Expected time, variance and standard deviation of each activity
2. What is the probability that the project will not be completed in 20 weeks?
3. If the project includes a penalty clause of Rs.1,000 per week for any delay beyond 19
weeks then what is the probability of paying a penalty of more than Rs. 5000?