Assembly line workers at Crane Manufacturing worked a total of 13300 direct labor hours to produce 37400
Fantastic news! We've Found the answer you've been seeking!
Question:
Assembly line workers at Crane Manufacturing worked a total of 13300 direct labor hours to produce 37400 units. The standard for producing one unit is 15 minutes at a wage rate of $11.3. If the actual wage rate was $11.8 per direct labor hour, Crane's direct labor rate variance is
Select answer from the options below
$4675 favorable.
$6650 unfavorable.
$4675 unfavorable.
$6650 favorable.