Assume a company that uses activity-based costing (ABC) has only two products A and B. The
Fantastic news! We've Found the answer you've been seeking!
Question:
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below:
Setups | Machining | Packing Orders | |||||||||
Activity measure quantity: Product A | 20 | 1,000 | 150 | ||||||||
Activity measure quantity: Product B | 20 | ? | 350 | ||||||||
Overhead cost per activity cost pool | ? | ? | $ | 10,000 | |||||||
Activity rate | $ | 150 | per setup | $ | 8 | per MH | ? | ||||
If the company decided to use a plantwide overhead rate with machine hours as the allocation base, what would be its plantwide overhead rate?
Related Book For
Posted Date: