At a 100% performance rate, the total number of labor hours required to produce a quantity of 1000 of Product X is 379. This is a new product that is difficult to assemble, and currently the production efficiency is at 65%. If the Marketing forecast is 16,000 per day, how many employees do we need to hire -- providing we have a one-shift operation and each employee works 8 hours per day?