At Briggs Company, the standard time required to assemble one transmitter is 2.30 hours. The standard wage
Fantastic news! We've Found the answer you've been seeking!
Question:
At Briggs Company, the standard time required to assemble one transmitter is 2.30 hours. The standard wage is $9.60 per hour. During June, employees at Briggs produced 860 transmitters and worked 1,935 labor hours at a total cost of $18,963. What is Briggs' labor rate variance?
A).$395.60 unfavorable.
B).$25.80 favorable.
C).$1,677.00 unfavorable.
D).$387.00 unfavorable.