b) Complete the following status reports for periods 1-4. Status Report: Ending Period 1 Task %...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
b) Complete the following status reports for periods 1-4. Status Report: Ending Period 1 Task % Complete 1 50% 2 3 Cumulative Totals Status Report: Ending Period 2 % Complete Finished Task 1 2 3 80% 75% Cumulative Totals 40% 25% +tatus Report: Ending Period 3 Task % Complete 1 Finished 2 3 4 5 6 Cumulative Totals Status Report: Ending Period 4 Task % Complete 1 Finished 2 3 4 5 6 7 80% Finished 50% 0% 33.3% Cumulative Totals 1 2 End of Period 3 Finished Finished Finished. 30% 66.7% 0% 4 EV 12 PCIB 12 6 30 EV 6 6 2 14 EV EV AC 13 SPI 3485 14 AC 6 8 3 17 AC 13 15 10 4 0 4 AC 13 18. 10 8 3 8 0 PV 12 c) Complete the following performance indexes summary table. CPI 10 8 30 PV 4 341 11 PV PV TCPI CV -1 -2 -2 -5 ($000) CV 0 -2 -1 -3 ($000) ($000) CV ($000) CV TSPI SV 0 2 -2 0 SV 2 3 -2 3 SV SV TCFR ACT/ WP 1 2 3 4 5 6 7 Schedule information DUR 2 3 2 2 2 3 1 ES 0 0 0 2 3 2 5 LF 3 3 2 5 5 5 6 SL 1 0 0 1 0 0 0 Total Baseline budget needs ($ 000) Time period 2 PV 0 12 15 3 8 4 4 6 10 9 5 1 48 375 3 4 5 33 6 33 4 3 5 Total PV by period 11 19 11 12 75 Cumulative PV by period 11 30 41 53 60 65 6 b) Complete the following status reports for periods 1-4. Status Report: Ending Period 1 Task % Complete 1 50% 2 3 Cumulative Totals Status Report: Ending Period 2 % Complete Finished Task 1 2 3 80% 75% Cumulative Totals 40% 25% +tatus Report: Ending Period 3 Task % Complete 1 Finished 2 3 4 5 6 Cumulative Totals Status Report: Ending Period 4 Task % Complete 1 Finished 2 3 4 5 6 7 80% Finished 50% 0% 33.3% Cumulative Totals 1 2 End of Period 3 Finished Finished Finished. 30% 66.7% 0% 4 EV 12 PCIB 12 6 30 EV 6 6 2 14 EV EV AC 13 SPI 3485 14 AC 6 8 3 17 AC 13 15 10 4 0 4 AC 13 18. 10 8 3 8 0 PV 12 c) Complete the following performance indexes summary table. CPI 10 8 30 PV 4 341 11 PV PV TCPI CV -1 -2 -2 -5 ($000) CV 0 -2 -1 -3 ($000) ($000) CV ($000) CV TSPI SV 0 2 -2 0 SV 2 3 -2 3 SV SV TCFR ACT/ WP 1 2 3 4 5 6 7 Schedule information DUR 2 3 2 2 2 3 1 ES 0 0 0 2 3 2 5 LF 3 3 2 5 5 5 6 SL 1 0 0 1 0 0 0 Total Baseline budget needs ($ 000) Time period 2 PV 0 12 15 3 8 4 4 6 10 9 5 1 48 375 3 4 5 33 6 33 4 3 5 Total PV by period 11 19 11 12 75 Cumulative PV by period 11 30 41 53 60 65 6
Expert Answer:
Answer rating: 100% (QA)
The provided images contain information needed to fill out the status reports for periods 14 which includes tasks with their percentage completion Earned Value EV Actual Cost AC Planned Value PV as we... View the full answer
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date:
Students also viewed these general management questions
-
Part A. You are in charge of the Aurora Project. Given the following project network, baseline, and status information, develop status reports for periods 18 and complete the performance indexes...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-6. On December 12, Irene purchased the building where her store is located. She paid...
-
Determine the length of the hydrogen bonds between: TYR41H and GLU37O ALA39H and MET35O GLU38H and ILE34O THR36H and ARG32O ARG32H and TYR28O by using PyMOL And identify the residues located at...
-
Because the neutron has no charge, its mass must be found in some way other than by using a mass spectrometer. When a neutron and a proton meet (assume both to be almost stationary), they combine and...
-
Find the largest nominal deficit that the government can run without raising the debt-GDP ratio, under each of the following sets of assumptions: a. Suppose that real GDP is 20,000 and remains...
-
Use the data for Atlantis Aquatics, Inc., from E4-21 A. Requirements 1. Prepare Atlantis Aquatics classified balance sheet. Use the account format. The balance shown for retained earnings represents...
-
RAR Corporations accounting records include the following items, listed in no particular order, at December 31, 2012: Income tax of 30% applies to all items. Requirement 1. Prepare RARs income...
-
Parkin Limited has budgeted to use 6,000 units of component Zed during the forthcoming year. Production will be distributed evenly throughout the year. Assume the company does not carry any safety...
-
Carter Enterprises is involved in the soybean business in South Carolina, Alabama, and Georgia. The president of the company, Earl Carter, goes to a commodity sale once a month where he buys and...
-
In a long cylindrical vessel made of perfectly conducting walls, an ideal mono-atomic gas is confined with the help of a light piston, which can slide inside the cylinder without friction. Number of...
-
Should the law allow noncompete agreements, but require employers to compensate employees in some way for signing them? What form should that compensation take? Is money enough, given an employer's...
-
Appointed as the CFO of an MNC , with a global presence, and manufacturing facilities in Asia, you are motivated to demonstrate your capabilities, with international financial management knowledge...
-
Partne 5) Gravitational, Electric, and Magnetic Fields If the earth had a charge of +18C and your projectile had a charge of +2.0C, what acceleration value would you use for a projectile motion...
-
A company is considering two alternative machines with different net cash flows and salvage values. Present value amounts are calculated using Excel and the results follow. Potential Machine...
-
What is the difference between arteries and veins structurally?What differences are seen between large and small arteries andlarge and small veins?what do the types of arteries and veins...
-
On 1/1/2014, PJ purchases a bond with a face value of 10,000 that pays annual coupons and the first coupon expires on 12/31/2014. The exchange value is 10,000. PJ pays 10,000 for bail. At the time of...
-
Ball bearings are widely used in industrial applications. You work for an industrial food machinery manufacturer and your role is to design the driveshaft assembly on a new type of equipment that...
-
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which...
-
The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Below are three projects under consideration. a. Using the scoring matrix below, which project would...
-
The National Oceanic Research Institute is planning a research study on global warming in Antarctica. The 16-month network schedule is presented below. It is followed by budgets for each activity....
-
Describe one occasion where you have been influenced to buy a product or engage in an activity as a direct result of an item of corporate communication, eg social media update; and explain what that...
-
What are the elements of a master budget?
-
Discuss the potential conflict between using a budget as a motivational device and as a means of control.
Study smarter with the SolutionInn App