What is the daily dose, expressed as a percentage, for a worker who operates a lathe 1for
Fantastic news! We've Found the answer you've been seeking!
Question:
What is the daily dose, expressed as a percentage, for a worker who operates a lathe 1for .5 hours per day, set his lathe up for 4.5 hours per day, performs administrative tasks for 1 hour per day, and spends the balance of his 8-hour workday either at breaks or eating lunch? Use the data below and calculate the dose using the OSHA PEL.
Time (hr)
SPL
(dBA)
Operating the lathe
95
Setting up the lathe
90
Breaks and lunch
84
Administrative tasks
82
120%
107%
94%
74%
2. Calculate the TWA.
89.5 dBA | ||
87.3 dBA | ||
86.2 dBA | ||
93.7 dBA |