Based on the following PERT analysis. For all high-level activities in this project, calculate the following: 1.
Fantastic news! We've Found the answer you've been seeking!
Question:
For all high-level activities in this project, calculate the following:
1. Optimistic time (5 marks)
2. Most likely time (5 marks)
3. Pessimistic time (5 marks)
4. Expected activity time (5 marks)
5. Standard deviation (5 marks)
6. Variance (5 marks)
7. For one date ahead of most likely completion date, calculate Z and hence the probability of completion by that date. (5 marks)
8. For one date behind the most likely completion date, calculate Z and hence the probability of completion by that date.