Below are the costs for each of the module of a project, Module 1: $40,000 Module
Fantastic news! We've Found the answer you've been seeking!
Question:
Below are the costs for each of the module of a project,
Module 1: $40,000 Module 2: $20,000 Module 3: $190,000 Module 4: $90,000 Module 5: $80,000
What is the cost baseline if the contingency reserve is 10% and management reserve is 5%?