Budget. Actual
Question:
Budget. Actual
5000 unit 5,500unit
Cost
direct material. 20000. 22764
direct labour. 60000. 75900
in preparing the flexed budget ,the following is available concerning were adopted
direct material 10kg of material per unit produced
direct labour 2 hour per unit produced
The following additional information is available concerning the actual output
- The actual usage of material in November was 54200kg and
- the wage rate increased to 6.60 per hour at the start of November
calculate a. Material price variance and material usage /quantity variance
b.labour rate variance and labour efficiency variance