Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider a project whose task XYZ budget is $12,000 with the start date of 5 Dec and end date of 15 Dec, by 11th Dec task is supposed to be 60% complete but actual percent completed is 40%. The actual cost of the task A is $4000.
Calculate the following:
- Schedule Variance
- Schedule Performance Index
- Cost Variance
- Cost Performance Index