Consider a simple process where work flows from Activity A to Activity B to Activity C to
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes and is performed by Aaron. Activity B takes 5 minutes and is performed by Aaron and Betty together. Activity C takes 4 minutes and is performed by Betty and David together. Activity D is performed by David and takes 3 minutes. What is the bottleneck of the process?
(a) None of these
(b) Activity B
(c) Betty
(d) Aaron
(e) Activity C