Consider the following information: PV = $ 3 0 0 , 0 0 0 , EV =
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following information: PV $ EV $ AC $ and BAC $ Use the schedule performance index SPI and cost performance index CPI values to determine how project is performing.A Project is on time, but over budget. Project is behind schedule and under budgetC Project is behind schedule and over budget.D Can't be determined with given information.