Consider We Build Construction's latest project: We Build is developing a 1-story medical office building on available
Question:
Consider We Build Construction's latest project: We Build is developing a 1-story medical office building on available land near a hospital. The following table details the project's 8 work activities.
K | Activity | Duration (days) | Predecessor Activities |
1 | Foundation | 15 | ‒ |
2 | Concrete slab | 3 | 1 |
3 | Structural members | 3 | 2 |
4 | Roof | 7 | 3 |
5 | Rough electrical | 10 | 3 |
6 | Heating and air conditioning | 13 | 1, 3 |
7 | Walls | 18 | 3, 5, 6 |
8 | Interior finish | 20 | 4, 7 |
a) After drawing the network based on the provided information (you do not need show the network), compute the early and late activity times, the total slack, and identify the critical path. Please provide me with the following information in order as your answer
The critical path (e.g., 1-2-3-4)
EF for activities 4, 5, 6 and the equation you use
LF for activity 8 and the equation you use
LS for activities 4, 5, 6 and the equation you use
Total slack for activities 2, 3, 8 and the equation you use
b) How will you draw the network if there are multiple starts? Please provide a brief description.