Cost-reimbursement contracts are most appropriate for projects that a. involve risk. b. take less than one year
Fantastic news! We've Found the answer you've been seeking!
Question:
Cost-reimbursement contracts are most appropriate for projects that
a. involve risk.
b. take less than one year to complete.
c. are well defined and entail little risk.
d. are with customers that want a single payment date.