Given the following indicators of a project: CV < 0 and SPI > 1. What is the
Fantastic news! We've Found the answer you've been seeking!
Question:
Given the following indicators of a project: CV < 0 and SPI > 1. What is the status of the project? On schedule and above cost Behind schedule and above cost On schedule and below cost Behind schedule and below cost