Data for six weeks from a carpeting crew is as follows:
Week | Crew Size | Yards Installed |
1 | 4 | 96 |
2 | 3 | 72 |
3 | 4 | 92 |
4 | 2 | 50 |
5 | 3 | 69 |
6 | 2 | 52 |
Compute the labor productivity (= yards installed per crew member) for each of the six weeks. Which week has the highest productivity?