A circular culvert is planned for a highway crossing. The culvert must handle 1.5 m 3 /s
Fantastic news! We've Found the answer you've been seeking!
Question:
A circular culvert is planned for a highway crossing. The culvert must handle 1.5 m3/s when the water depth is 2.5 m (or less), as measured from the invert of the culvert. Assuming that the culvert operates with inlet control, and the discharge coefficient Cd is 0.61, what is the minimum required culvert diameter (in mm)?