Determine the optimal solution. Project: 1 2
Fantastic news! We've Found the answer you've been seeking!
Question:
Determine the optimal solution.
Project: 1 2 3 4 5
Cost: $230,000. $280, 000. $290,000. $205,000. $270,000
Net Present Value: $630,000 $400,000 $760,000 $620,000 $460,000
What is the total net present value of these projects?
Total net present value:
Keeping in Mind that
Project 1 - be selected Project 2 not be selected Project 3 be selected Project 4 not be selected Project 5 will be selected