- Draw the project network using the AON approach. Use a START and/or END nodes as needed.
- Using the normal times and normal costs:
- Calculate the ES, EF, LS and LF of each activity.
- Calculate and show in the nodes of your AON project network the total slack of the non-critical activities.
- What is the normal (duration) time of the project?
- What are the critical activities and the critical path?
Activity | Predecessor | Normal time (days) |
A | - | 4 |
B | A | 9 |
C | B | 4 |
D | A | 7 |
E | D | 4 |
F | D | 5 |