The project management has established that to make 1000 conductors the following costs will be incurred, direct
Fantastic news! We've Found the answer you've been seeking!
Question:
The project management has established that to make 1000 conductors the following costs will be incurred, direct materials $70 000, direct labour $26 000, variable and fixed overheads $15 000 each respectively. The project manager can purchase the 1000 conductors externally for $125 000. The avoidable fixed costs are $5 000 if the units are purchased externally. What are the cost savings if the project manager makes the conductors?
A) $1 000
B) $5 000
C) $10 000
D) $4 000