Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct
Fantastic news! We've Found the answer you've been seeking!
Question:
- Following is a table listing the project activities, sequencing requirements and other relevant information:
Expected Time | Direct Cost | ||||
Activity | Preceded By | Regular | Crash | Regular | Crash |
A | -- | 6 days | 2 day | $2000 | $3800 |
B | -- | 12 | 6 | 2000 | 10000 |
C | A | 4 | 2 | 1000 | 4000 |
D | B, C | 10 | 6 | 3400 | 4600 |
E | D | 8 | 6 | 2800 | 3900 |
F | E | 6 | 2 | 5000 | 7600 |
G | B, C | 18 | 8 | 16000 | 19600 |
H | F, G | 6 | 4 | 2000 | 4000 |
Construct a network including the Early and Late Start and Finish times.
Identify the normal Critical Path(s) and the normal expected completion time
Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?