For 4 investment options that a city is considering, which of the below statements is true? Rate
Fantastic news! We've Found the answer you've been seeking!
Question:
Rate | 14.00% | per year | ||
Project | Initial cost | Life of project | Salvage Value | Annual benefits |
A | ($6,545,000) | 8 | $593,000 | $1,605,000 |
B | ($8,328,000) | 10 | $675,000 | $1,212,000 |
C | ($9,674,000) | 12 | $2,262,000 | $1,722,000 |
D | ($8,546,500) | 7 | $674,000 | $1,228,000 |
Group of answer choices
Choose Option D as the incremental B/C ratio between it and its final competitor is 1.55.
Choose Option D as the incremental B/C ratio between it and its final competitor is 1.20.
Choose Option A as the incremental B/C ratio between it and its final competitor is 0.97.
Choose Option A as the incremental B/C ratio between it and its final competitor is 0.45.