For the data as follows, draw the AOA diagram and identify the critical path. What is the length of the critical path?
Activity | Immediate Predecessors | Days |
A | - | 5 |
B | A | 2 |
C | A | 4 |
D | B | 5 |
E | B | 4 |
F | C | 4 |
G | E, F | 2 |
H | D | 3 |
I | G, H | 5 |