Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company
Fantastic news! We've Found the answer you've been seeking!
Question:
Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | |
---|---|---|---|---|
Machining | Machine-hours | $ 213,400 | 11,000 | MHs |
Machine setups | Number of setups | $ 61,600 | 140 | setups |
Production design | Number of products | $ 78,000 | 2 | products |
General factory | Direct labor-hours | $ 244,000 | 10,000 | DLHs |
Activity Measure | Product Y | Product Z |
---|---|---|
Machining | 7,400 | 3,600 |
Number of setups | 60 | 80 |
Number of products | 1 | 1 |
Direct labor-hours | 7,400 | 2,600 |
13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z?