Here is some data for Project "XYZ"
Budget | $ 5,276 thousand |
Start Workday | 7 |
Finish Workday | 109 |
Reporting Day | 34 |
Earned Value | $ 262 thousand |
Planned Value | $ 364 thousand |
Actual Cost | $ 741 thousand |
Using a "Do-Nothing" forecast, estimate the extra amount of money that will need to be added to (or subtracted from) the budget, in thousands of dollars, rounded to the nearest integer number of thousands. The allowed error margin is 2% or 1 thousand dollars, whichever is larger.